Project Profiles

  • System Installation Rio Hondo, TX

    Objective: Install experimental algae cultivation farm on flatlands of Texas. Solution: SCE is the prime contractor installing an algae cultivation test facility on an 1,880-acre parcel located at the southernmost tip of Texas in the town of Rio Hondo.

  • Impacted Soil New Providence, Bahamas

    At Cable Beach in New Providence, Bahamas, SCE was contracted to perform all field work associated with the cleanup of a 500,000 gallon fuel oil release that occurred on the future home of the $3.5 Billion Baha Mar MegaResort. It was the largest environmental cleanup ever to be completed in the Bahamas.

  • Tight Space Soil Remediation Brooklyn, NY

    Objective: Perform deep soil excavation and remediation at a former service station in a congested area and tight space.

  • Abatement/Demolition Grand Cayman, Cayman Islands

    Pursuant to a contract with the Ministry of Education, Employment and Gender Affairs of the Cayman Islands Government, SCE’s crews completed the environmental abatement and demolition of a portion of the John Gray High School in George Town, Grand Cayman, as the first phase of a project with a critical construction deadline later in the year.

  • Lagoon Closure Project Columbus, OH

    SCE was contracted to provide closure services of a RCRA Solid Waste Management Unit (SWMU) in Columbus, OH in several Phases over a six (6) year period.

  • Tetrachloroethene Tampa, FL A

    Objective: Remove soil contaminated beneath the concrete slab of a Dry Cleaning operation on the ground floor of a Luxury Hotel.

  • Brownfield Remediation – Lome’, Togo, West Africa

    In Togo, West Africa, SCE was awarded a contract for the decontamination and tank cleaning of 34 above ground storage tanks ranging in size from 25,000 to 500,000 USG, and the fluid elimination of over 462,000 gallons of product.

  • Tank Decommissioning – St. Croix, USVI

    SCE was awarded a series of contracts for the assessment, tank cleaning, abatement, decontamination and demolition at the ESSO facility at the Henry E. Rholsen International Airport.

  • Stormceptor Installation – Blue Bell, PA

    SCE was contracted to install a Stormceptor component to an existing stormwater drainage system.

  • Airport Fuel Farm – JFK International Airport, NY, NY

    SCE is the Prime Contractor on a multi-year contract for the operation and maintenance of the bulk fuel farm and satellite fuel farm at the John F. Kennedy Airport in New York. This $3MM multi-year contract provides remediation services for jet fuel release at both fuel farms as well as maintenance of pumping equipment at the site.

  • Landfill Remediation Frewsburg, NY

    SCE was retained by the NY Department of Environmental Conservation for the remediation of a landfill Superfund Site in Frewsburg, NY. The landfill operated as a municipal solid waste and industrial waste landfill from the early 1960’s to 1979.

  • World Trade Center New York, NY

    Provide support for decontamination and demolition efforts following the September 11th, 2001 World Trade Center tragedy. This project was conducted in accordance with City of New York Mayor’s Office of Emergency Management and FEMA.

  • Transmission Line Tower Demolition Northeastern Pennsylvania

    Demolish a series of one-hundred fifty foot tall transmission line towers throughout Northeastern Pennsylvania.

  • Row Home Demolition Chester, PA

    Demolish 214 Row Homes and install new infrastructure for a new townhome development on the I95 corridor near the Commodore Barry Bridge.

  • Row Home Demolition Allentown, PA

    Total demolition of 322 homes and site improvements.

  • Rosehill Cemetery Linden, NJ

    Restore a portion of a century-old cemetery after a storm surge from Hurricane Sandy deposited oil onto the surface of the cemetery.